Secondary Flotation Plant

Construction, 2026

Secondary Flotation Plant

A secondary flotation circuit engineered to recover gold locked in tailings and transform 1.4 million tonnes of dormant material into value, relieving pressure on the main plant while improving water recycling and reducing environmental waste.

LocationTaraba State
CommodityGold (recovered from tailings)
StageConstruction, 2026
ScopeSecondary flotation circuit
Feedstock1.4 million tonnes of dormant tailings

Overview

A secondary flotation plant engineered to recover gold locked in tailings and convert dormant material into value, relieving pressure on the main plant while improving water recycling and reducing environmental waste.

The project turns a waste liability into a revenue stream, and is a working example of the green-mining principles Terra-Tara applies across its operations.

Project highlights

  • Recover gold locked in tailings from Levees 6 and 7
  • Transform 1.4 million tonnes of dormant tailings into value
  • Relieve pressure on the main plant while maintaining overall throughput
  • Reduce environmental waste and improve water recycling and management

Progress to date

Civil works across the plant footprint are complete.

  • Flotation concentrate, condition and tails tank plinths completed
  • Blower base plinths completed
  • Main cell plinths, bundwalls and sump completed

Next phase

  • Begin earthworks for the raw water tank
  • Complete drainage design and set-out
  • Receive the next batch of flotation equipment
  • Complete mechanical installation adjudication and electrical and instrumentation quotations